                                             Abstract:This paper introduces the technology of installation and commissioning of the bucket reclaimer system with a 
capacity of 6 000 t/h for Huanghua Port Expansion Project. Based on the site conditions and the status of delivery of 
equipment, the technological process for installation of the bucket reclaimer system was decided;the calculation of hoisting 
parameters was made for rational selection of proper cranes and riggings;and rational and efficient quality control measures 
were taken, thus ensuring the quality and safety of installation and commissioning and improving the efficiency of installation 
and commissioning to achieve the planned results. 
                                         |